Info travaux 

2024-11-16 Work on Saturday, November 16

Work will take place on the construction site on Saturday, November 16. An electrical team will be working indoors. This work will be carried out quietly.

At the same time, a small team will be working outside to prepare the site for winter. It is possible that you will hear the sound of transport vehicles backing up.

Thank you for your understanding.

The HOP Lachine! team

2024-05-02 Dismantling of the construction crane on May 9

On Thursday, May 9, 2024, workers will dismantle the crane on the worksite. Heavy vehicles will arrive around 6 a.m. and turn off their engines until 7 a.m. Parking will be prohibited on rue Saint-Antoine as shown on the attached map.

No-parking signs will be installed the day before to accommodate transport trucks. Traffic will be allowed and controlled by signallers. The street may be closed briefly, if necessary.

The standard time taken for this type of dismantling is usually between eight and ten hours. Therefore, the work will be completed on the same day.

All safety precautions will be taken in the area affected by the work.

Site-plan-Lachine

2024-04-10 Worksite activity this Saturday, April 20

Electrical work will be carried out this Saturday, April 20, at the Lachine Hospital construction site. This work will not affect traffic on neighboring streets.


We wanted to keep you informed

2023-12-12 Partial closure of 16th Avenue

Due to concrete work, 16th Avenue will be partially closed from the corner of rue St-Antoine to rue Provost. 

This closure will be in effect Tuesday, December 12, 7 a.m. to 6 p.m. and Friday, December 15, from 7 a.m. to 6 p.m.

Signage will be in place and a signaller will be present to guide emergency vehicles and local traffic. 

2023-11-10 Complete closure of 16th Avenue

Work to connect municipal sewer pipes and install a fire hydrant requires the complete closure of 16th Avenue from the corner of rue St-Antoine to the hospital's main entrance. 

The closure is scheduled from Monday, November 13 at 7 a.m. until Wednesday, November 15 at 6 p.m. Depending on weather conditions, paving work could extend until Friday, November 17. 

Signage will be in place and a flag person will be there to direct  emergency vehicles and those in the immediate neighbourhood. Authorized vehicles will only be allowed to pass to the south.

2023-09-22-Lachine Hospital modernization - A note to our neighbors

The Lachine Hospital expansion site is bordered by the following streets: 13th Avenue, Saint-Antoine Street and 16th Avenue. Space is at a premium. This poses a challenge for worksite management, and may have an impact on the surrounding neighborhood.

The HOP Lachine team is working with the construction manager (AXOR) to ensure compliance with City of Lachine regulations. Work is authorized seven (7) days a week, from 7 a.m. to 9 p.m.

Weekend work is rare, but sometimes necessary in exceptional situations.

If heavy trucks (concrete mixers, formwork deliveries, etc.) are required to operate on the streets, the contractor must ensure that the available space is clear and safe for pedestrians and vehicles.

The contractor responsible must obtain required permits from the city, and install signs indicating a parking restriction the day before the work.

Where necessary, flag persons will be present to regulate traffic flow and assure pedestrian safety.

The contractor is responsible for removing signs and cleaning up the street and sidewalks after work has been completed.

We understand the inconvenience caused by the construction, but the site is progressing at a good pace and we are confident that the impact on the population will diminish over time.

Thank you for contacting us by e-mail. It helps us keep track of operations and notify the appropriate parties.

The HOP Lachine project team

2023-09-19 Info travaux - Work affecting parking areas

New fencing will be installed on the Lachine Hospital construction site. There will be no parking along the north side of St-Antoine Street on September 20 and 21.

Signs will be posted, indicating no parking between 6:00 a.m. and 6:00 p.m. on September 20 and 21, and if necessary, on September 22. Cones and security tape will also be installed for everyone's safety.

A traffic control person will be present as materials are unloaded. Thank you for your understanding. 

2023-09-16 Info travaux - Construction work on Saturday, September 16

Please note that, exceptionally, concrete work will take place this Saturday, September 16, from 7 a.m. to 4 p.m. Finishing work will then take place until 8 p.m. Examination of the slab will continue from 8 p.m. to 10 p.m. Slab inspection work will not be noisy, but will require lighting equipment.

Thank you for your understanding.

2023-07-15 Info travaux - concrete work on Saturday, July 15 

Please note that there will be concrete work on Saturday, July 15 at the Lachine Hospital, which will affect traffic on 13th Avenue.

2023-06-19 Info travaux - Lachine Hospital - Street Closed

Please note that on Tuesday, June 20, starting at 6 a.m., the sidewalk and 16th Avenue, opposite the work site, will be closed from rue St-Antoine to allow concrete pouring for the foundation walls. The sidewalk on the west side will be open, and flagmen will be on site. Access to the hospital will be maintained via rue Provost.

2023-05-19 Info travaux - Lachine Hospital – Oxygen tank management

Please note that the installation of the new oxygen tanks took place on Thursday, May 18. 

The change had no impact on current operations. 

During the planned emptying of the old tanks, scheduled for Tuesday, May 23 after 5 p.m., there will be a slight hissing noise and a white cloud will appear on the ground.  This is completely normal and harmless. 

2023-05-05 Info travaux - The first pour of the foundation

On April 14th, the first concrete for the foundation of the future Lachine Hospital was poured.The start of the foundation also means that excavation work is almost finished. Since April 14th, whole walls have also been poured and the forms have been removed. The old oxygen tanks will soon be replaced by new ones. Those are scheduled to arrive on May 9. They will be installed soon after. The next week, purity and compliance tests will be done. Once everything is certified, the tanks will begin operating unnoticed, meaning with no interruption and no impact on service.

2023-03-30 Info travaux — Weekend work announcement — HOP Lachine

Work will take place on Saturday, April 1, between 7 a.m. and 5 p.m. and on Sunday, April 2, between 9 a.m. and 4 p.m., to prepare for the casing work that will take place next week. We apologize for any inconvenience this may cause.

2023-03-24 Info travaux — Saturday excavation work — HOP Lachine

The excavation contractor for the the Lachine Hospital modernization project has informed us that they have discovered a layer of very hard rock at the construction site, so excavation work must continue on Saturday, March 25. This exceptional weekend work will begin at 7:00 a.m., in accordance with applicable regulations. We apologize for any inconvenience this may cause. 

2023-03-16 Info travaux — excavation work — HOP Lachine

Exceptionally, the contractor will have to continue the excavation work on Saturday, March 18, at the Lachine Hospital. Work will begin at 7 a.m. in accordance with regulations. Trucks will have to circulate around the site. This exceptional situation is necessary because of the thaw period that goes into effect Monday, March 20.We apologize for any inconvenience this may cause.