Construction Update on the MUHC’s Glen site

  • Start-up of the Cancer Centre’s electromechanical systems is complete.

  • Finishing work such as painting, installation of ceramic flooring as well as installation of furniture is currently being carried out in different blocks.

  • Dynamic testing of the 11 emergency generators in Blocks B, C, D and the shelters for the generators in Block E are now complete and will soon be commissioned.

  • Finishing of the external shell of Blocks A to D in coloured aluminum is well underway. Of the 28,000 panels, more than 16,000 have been installed, which
    accounts for approximately 60% of the total.

  • Landscaping will resume in April 2014 and is expected to be completed by September 2014.
  • The call for tenders for commercial spaces should be issued at the end of winter 2014. There will be between 20 and 30 retail services for patients, visitors and employees. The types of services planned are: coffee shops, restaurants, gift shops, a florist, and a pharmacy.

  • Currently, there are approximately 1,300 workers and 400 professionals working on the Glen site.

 